对乐滩水电站初期及正常运行情况下的运行方式进行分析研究,使其运行方式在确保枢纽工程和机组的安全、稳定的前提下,充分发挥电站在系统中的作用,提高发电效益。
The paper analyzes and researches the operation modes in the initial operation period of Letan hydropower station and under the conditions of normal operation, on the premise of ensuring pivotal project and units to be safe and stable, the modes call hydropower station into full play in the systems and improve power benefit.
出处
《红水河》
2006年第2期35-38,共4页
Hongshui River
关键词
运行方式
正常蓄水位
分析研究
乐滩水电站
operation mode
normal storage water level
analysis and research
Letan hydropower station