期刊文献+

基于蚁群算法的试验流程优化研究 被引量:5

Test scheduling based on ant colony optimization
下载PDF
导出
摘要 水中兵器的海上试验涉及许多人员、兵力、被试产品、测量设备等,试验周期长、消耗大,因此如何缩短试验周期是亟待研究解决的问题.文中首先将试验流程优化问题转化为车间调度问题,建立了相应的数学模型,再应用蚁群算法转移规则得到中间结果并进行排队以对各种资源约束进行处理.最后将结果利用局部搜索算法优化后作为蚁群算法信息素更新的基础.实例计算结果表明,该方法优化效果良好. With regard to much manpower, forces, under-proof products and measurement equipment, the sea tests for underwater weapons will take a long period and great expenditure. Therefore, the test scheduling is what needs to be dealt with. The test scheduling is first converted into a job shop scheduling problem. The corresponding mathematical model is established. Then the transition rules of ant colony algorithm are adopted to obtain intermediate result before the queuing theory is used to deal with different resource constraints. Finally, a local search method is used for further optimization before the pheromones of ants are updated. The simulation results prove the validity of the algorithm.
出处 《海军工程大学学报》 CAS 北大核心 2006年第3期38-42,共5页 Journal of Naval University of Engineering
关键词 蚁群算法 车间调度问题 水中兵器 ant colony optimization job shop scheduling problem underwater weapon
  • 相关文献

参考文献7

二级参考文献18

  • 1王滨,周云晖,王俊峰,云庆夏.双层卫星网络QoS路由算法研究[J].无线通信技术,2005,14(2):22-27. 被引量:2
  • 2Dorigo M, Maniezzo V, Colorni A. The Ant System: Optimization by a Colony of Cooperating Agents. IEEE Transactions on Systems,Man,and ?D瑈bernetics-Part B, 1996,26(1):1-13.
  • 3Besten M D, Stutzle T, Dorigo M. Ant Colony Optimization for the Total Weighted Tardiness Problem. Parallel Problem Solving fromNature - ?D?PSN Ⅵ 6th Intemational Conference, 2000.
  • 4Sjoerd V, Zwaan D, Marques C. Ant Colony Optimization for Job Shop Scheduling. http://citeseer.nj.nec.com/vanderzwaan99ant.html.
  • 5Peeters P, Brussel H V, Valckenaers P. Pheromone Based Emergent Shop Floor Control System for Flexible Flow Shops. Artificial Intelligence ?D?n Engineering ,2001,15:343-352.
  • 6Stutzle T, Darmstadt T U, Alexanderstr. An Ant Approach to the Flow Shop Problem. http://citeseer.nj.nec.com/273051.html.
  • 7Zimmermann H J. Application of fuzzy sets theory to mathematical programming[J]. Information Science, 1985, 36: 29-58.
  • 8Chun J S, Jang H K, Hahn S Y. A study on comparison of optimization performances between immune algorithm and other heuristic algorithms[J]. IEEE Trans. on Magnetics, 1998, 34(5): 2972-2975.
  • 9Xu Z H, Gu X S. A Hybrid Method for Scheduling Problems of Flow Shop[ A]. In: Proceedings of the 5th World Congress on Intelligent Control and Automation, WCICA'04 [ C]. Hangzhou: the Institute of Electrical and Electronics Engineers, Inc, 2004. 4:2928-2932.
  • 10徐震浩 顾幸生.用模糊截集解决不确定条件下的具有中间存储时间有限的flow shop调度问题[A]..Proceedings of the 5th World Congress on Intelligent Control and Automation, WCICA''04[ C].Hangzhou: the Institute of Electrical and Electronics Engineers, Inc,2004.4.2923-2927.

共引文献41