摘要
结合工程概况,分析确定了承台施工方案,介绍了主墩承台钢板桩围堰的施工工艺,并对主要构件的受力做了验算,结果表明达到了类似地上作业的效果,解决了江水地区承台施工的问题。
Combined with general engineering situations the construction scheme of bearing platform is determined. The construction technology of steel-sheet-pile cofferdam of bearing platform is also introduced. Force analysis and checking computation show construction meet anticipated effect, which resolve bearing platform construction problems in river region.
出处
《山西建筑》
2006年第13期337-338,共2页
Shanxi Architecture
关键词
主墩承台
内撑系统
钢板桩
围堰
bearing platform of main pier, internal support system, steel-sheet-pile, cofferdam