摘要
在长庆油田的银川基地采用强夯法处理饱和液化软土地基取得良好效果。本文介绍了银川基地的地质概况、强夯试验方法和结果分析。证明强夯法对提高建设速度、降低工程造价作用显著。
It has been proven that the success results were achieved by using heavy-tamping method for the treatment of salurated liquefying soft foundation in Yinehuan base, Changqin oilfield. This paper presents the geological properties, the heavy-tamping treatment method and the result analysis. It shows that this method is efficient to shorten the construction period and reduce the cost of projects.
出处
《石油工程建设》
北大核心
1996年第4期30-34,共5页
Petroleum Engineering Construction
关键词
软土基
预处理
现场试验
油田开发
Yinchuan basin, Soft ground, Pretreatment, Field testing