吉林台一级水电站低温季节混凝土施工 被引量:2

Concrete Construction in Lower Temperature Season at Jilintai-ⅠHydropower Station
下载PDF
导出
摘要 吉林台一级水电站因工期原因,深孔泄洪洞进水塔1349~1356m高程混凝土及导流洞永久堵头混凝土施工必须在冬季进行。深孔泄洪洞进水塔等部位的混凝土浇筑采用了暖棚法,经计算表明,该方法满足施工要求。此外,混凝土浇筑还采取了一系列的温控及养护措施,这些经验可为类似工程提供参考。 Because of restriction of the construction period in Jilintai- Ⅰ Hydropower Station, the concrete for the low level power intake tower between elevation 1349m and 1356m and the permanent concrete plug for the diversion tunnel had to be placed in the winter season. Therefore, warm enclosure method was applied for concrete pours at low level power intake tower and low level spillways. It was indicated by calculations that the placing method meets the construction requirements. In addition, a series of temperature control and curing measures were taken during the concrete placement. All these experiences may provide information useful to similar projects.
作者 黄成 王石连
出处 《水力发电》 北大核心 2006年第6期37-39,共3页 Water Power
关键词 严寒气候施工 温控措施 暖棚法 吉林台一级水电站 construction under cold weather temperature control measures warm enclosure placing method Jilintai- Ⅰ Hydropower Station
  • 相关文献

同被引文献20

引证文献2

二级引证文献14

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部