摘要
详细介绍了江苏沙洲电厂2号机组定子吊装工艺的选择、施工难点及技术措施,基于实际情况,采用汽轮机基座侧面提升定子的工艺,为发电机定子的吊装提供了新的思路。
This article details the technique selecting, the main difficulties and the technical measures in No. 2 steam turbine stator hoisting in Shazhou Power Plant, Jiangsu Province. Based on the field situation, technique with the side of turbine base- plate to install the stator is shown, which inspiring a new method for electric generator stator's hoisting.
出处
《河北电力技术》
2006年第3期52-54,共3页
Hebei Electric Power
关键词
发电机
定子吊装
基础侧面
液压提升装置
electric generator
stator hoisting
side of the base platet hydraulic pressure hoisting device