摘要
根据黑龙江省电力干线OPGW光缆施工的经验和方法,以哈热厂-哈东变光缆工程为例,重点讲述OPGW光缆架设过程中,运用带电跨越方法进行“地线牵引光缆”施工,既满足光缆架设施工工艺要求,又保证了被跨越线路正常运行。
The thesis is based on experience and technique during the construction of OPGW optical Cable of Heilongjiang electrical power line, and according to thermal power station Hadong substation project , describes the construction of ground-line traction optical cable by means of electrification span during the erect of OPGW optical cable , which both makes the constrction of optical cable measure up and makes sure the Spanned line work well.
出处
《电力勘测设计》
2006年第3期65-69,共5页
Electric Power Survey & Design