摘要 杭州湾跨海大桥南岸滩涂区是大桥施工的咽喉工程,其上部结构采用50m箱梁整体预制、梁上运梁施工工艺。结合施工环境特点,分析了50m整体预制箱梁施工特点与难点,并提出相应的工程对策。 The part of Hangzhou Bay Bridge at the tidal flat area on the south bank is a vital link in the construction of the overall Bridge. The superstructure of the part of the Bridge is designed as 50-m span concrete box girders that are constructed with integral precasting technology, and are delivered to their erection sites via erected girders. In accordance with the construction environment of the Bridge, the construction features and challenges of the 50-m span girders are analyzed and corresponding countermeasures against the challenges are provided as well.
作者 匡明
出处 《桥梁建设》 EI CSCD 北大核心 2005年第B06期157-160,共4页 Bridge Construction
关键词 预应力混凝土结构 预制梁 箱形梁 施工工艺 施工方法 prestressed concrete structure precast girder box girder construction technology construction method
  • 相关文献

同被引文献21

引证文献2

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部