本文针对目前网络计划工期—成本优化实际应用中存在的几个问题进行了分析研究,并结合大型工程提出解决方法,从而使网络计划工期—成本优化更具实用性。
Three main problems in application of network plan time-cost optimization, which are how to establish direct cost-time relation and indirect cost-project duration curve, are analyzed in this paper. And then the solving approaches to large network are developed. These approaches make time-cost optimization more applicable.
出处
《北京建筑工程学院学报》
1996年第3期118-126,共9页
Journal of Beijing Institute of Civil Engineering and Architecture
关键词
网络计划
工期
成本优化
施工管理
工程网络
network plan
activity cost-time relation
time-cost optimization
indirect cost-project duration curve