三峡船闸薄衬砌墙混凝土施工技术

Concrete construction technique for thin-lining wall of ship lock for Three Gorges Project
下载PDF
导出
摘要 针对船闸闸室衬砌墙的高直立、薄壁、仓内结构复杂、工序交叉作业干扰大、工期紧且“观瞻性”质量要求高、安全隐患多等特点,成功研制并实施了“单侧分离式滑模”和“单侧滑框倒模”施工技术。实践证明,它具有速度快、安全性好、能保证混凝土“内实外光”等优点,填补了国内单侧滑模技术空白,均获得了国家新型实用专利。 In accordance with the requirements on the chamber of the ship lock for Three Gorges Project, such as the high vertical thin wall with complicated interior structure, disturbance from of the crossing-constructions, limited construction period, high quality requirement for sightseeing as well as the characteristics of more safety hidden troubles, the construction techniques of "One-side Separated Slip Forms" and "Shp-framed Reverse Mould" are successfully developed and conducted. The practice shows that the techniques have the advantages of high construction speed, better safety; with which not only the quality of "smooth outside with compacted inside" is guaranteed, but the blank of the technique of One-side Slip Forms at home is also filled up. Both the techniques have gained the national new practical patents.
出处 《水利水电技术》 CSCD 北大核心 2006年第7期57-59,共3页 Water Resources and Hydropower Engineering
关键词 三峡船闸 薄衬砌墙 滑模 混凝土施工 ship lock of Three Gorges Project thin-lining wall slip form concrete construction
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部