摘要
在分析宝钢EMS电力计量自动检测原系统存在问题的基础上,提出了宝钢电力计量系统的两种改造方案并对这两种改造方案进行了比较,同时探讨了方案的实现方法。
Based on analyzing the problems existing in the original auto-detection system for EMS electric power measurement in Baoshan Steel and Iron Complex, this paper puts forward two transforming schemes for the electric power measuring system in Baoshan Steel and Iron Complex, compares the two schemes, and probes into the methods for realizing these schemes.
出处
《科技情报开发与经济》
2006年第14期151-152,共2页
Sci-Tech Information Development & Economy
关键词
电力计量系统
改造方案
宝钢
electric power measurement
transforming scheme
Baoshan Steel and Iron Complex