摘要
结合工程实例,叙述了在楼板承载力不足以承担钢骨柱重量的情况下,采用重型吊车加自爬式三角拔杆人工吊装方案,避免了钢骨柱直接放置在楼面,保证了楼板的质量,加快了施工进度。
By the example of project, the article described the hoisting scheme which uses the heavy crane and manual hoisting by self-climb trigonal button pole when the floor can' t bear the weighet of steel skeleton pillar. Beacause the means avoid the steel skeleton pillar putted to the floor direct, it can assure the floor quality and speed up the construction progress.
出处
《山西建筑》
2006年第16期117-118,共2页
Shanxi Architecture
关键词
钢骨柱
吊装
重型吊车
steel skeleton, pillar hoisting, heavy crane