水布垭水库初期蓄水时机决策研究 被引量:5

Analysis of Initial Impounding Time for Shuibuya Reservoir
下载PDF
导出
摘要 结合清江梯级上游水布垭水库导流洞封堵时机选择中涉及到的各种影响因素,对工程及流域防洪安全、下游水库发电效益、河道断流时间等问题进行了研究分析。经多年历史实测资料演算,建议在2006年9月下旬封堵导流洞。该方案有助于减少断流时间,从而减少对下游的负面影响,以获得最大的经济效益。 Discussed in this paper are various factors affecting the opportunity of sealing off the diversion tunnel of the Shuibuya Reservoir of the Qingjiang Cascade Reservoirs, including basin flood control, downstream hydropower generation benefit and flow interception time. On the basis of historical data routing and analysis, it is suggested that the diversion tunnel be sealed off in the last ten days of Sept, 2006. The proposed scheme will help reduce the flow interception time and the negative influence on the downstream, thus generating the maximum economic benefit.
出处 《水电自动化与大坝监测》 2006年第4期73-76,80,共5页 HYDROPOWER AUTOMATION AND DAM MONITORING
关键词 水库 蓄水 防洪 发电 经济效益 reservoir water impoundment flood control power generation economic benefit
  • 相关文献

参考文献6

二级参考文献10

共引文献57

同被引文献33

引证文献5

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部