摘要
35kV/2kA超导电缆系统的研制,已经完成,并于2004年4月并入云南昆明220kV普吉变电站输电网络正式运行。该文介绍了普吉超导电缆系统现场安装和调试,总结了其运行情况,分析了电缆系统在一个大修周期内的故障和缺陷情况。普吉超导电缆系统现场的安装、调试和运行管理,能够适应电力系统相关规范的要求,在电网的统一调度下,实现安全送电1.6亿度。
35kV/2kA high temperature superconductor (HTS) cable system was developed suecessfully, and operated in the power grid in Kunming Puji 220kV substation in April 2004. This paper introduced the installation and test of Puji HTS cable system, summarized the operation status, and analyzed the fault and limitation in an operation period. The installation, test and operation management of Puji HTS cable system could adapt to related criterions of power industry. Under the grid control, the HTS cable system had transmitted power energy about 1.6 hundred million kilowatt-hours.
出处
《低温与超导》
CAS
CSCD
北大核心
2006年第4期293-298,共6页
Cryogenics and Superconductivity
基金
国家"863"计划支持(2002AA3061542004AA306110)
关键词
高温超导
电力电缆
运行
缺陷
High Temperature Superconductor (HTS), Power Cable, Operation, Fault