本文通过分析设计与采办在工程项目中的普遍性与特殊性,阐述了设计与采办之间协调的重要性,并通过一些实例,介绍在海南气体处理厂主体工程中如何加强设计与采办的协调,说明设计与采办之间的协调配合是影响工程建设项目施工进度和成本控制的关键因素。
This paper analyzes the popularity and speciality of design and procurement in the project, presents importance of coorchination between design and procurement. It also introduces how to strengthen coordination by giving some examples. The coordinating between design and procurement is the key elements to effect the schedule and cost control.
出处
《中国海上油气(工程)》
1996年第6期19-20,共2页
China Offshore Oil and Gas