摘要
结合加氢裂化装置目前的实际情况,分析了装置加工高含硫原料油后生产可能出现的问题,以及设备管线的耐腐蚀性能,并提出了相应的措施。
The effect to hydrocracker of processing row oil with high sulfur was analyzed as well as the corrosion resistance of pipe line. The countermeasures were. also put forward.
出处
《化学工程师》
CAS
2006年第8期66-69,共4页
Chemical Engineer
关键词
加氢裂化
高含硫原油
腐蚀
应对措施
hydmerack
mw oil with high sulfur
corrosion
countermeasure