青藏铁路格拉段铺轨架梁工程施工组织方案研究 被引量:3

Study of project scheme of track laying and bridge erection of Qinghai-Tibet Railway between Geermu and Lasha
下载PDF
导出
摘要 青藏铁路格尔木至拉萨段建设难度大、标准高、工期紧,控制全线总工期的为铺轨架梁工程,若用常规的施工组织方案安排施工,则不能满足总工期要求。进行多方案比选后,选择在安多设置铺架基地、制梁厂、制轨厂,可以向唐古拉山和拉萨2个方向进行铺轨架梁施工。该方案可节省部分投资、缩短工期、保证质量,是一个能够满足总工期要求的可行方案。 With high standard and short construction period, the construction of Qinghai - Tibet Railway was very difficult. The total construction time of the railway was decided by the scheme of track laying & bridge erection. If the normal project scheme was used, the planed construction scheme would not meet the need of total construction period of the railway. After comparing some project schemes, it is selected that the base of track laying & bridge erection, the bridge girder factory and track & tie factory will be built. The construction of track laying & bridge erection has two directions: to Tanggula Mountain and Lasha City. Under this scheme construction fee can be spared, the construction period can be shortened, quality of engineering can be guaranteed. It is proved to be an able project scheme which can meet the need of total construction period of the railway.
作者 李宁
出处 《铁道科学与工程学报》 CAS CSCD 北大核心 2006年第3期47-51,共5页 Journal of Railway Science and Engineering
基金 铁道部重点项目(2001G001-C-01)
关键词 青藏铁路 铺架工程 施工方案 Qinghai - Tibet Railway engineering of track laying & bridge erection project scheme
  • 相关文献

参考文献6

共引文献3

同被引文献12

引证文献3

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部