摘要
从封闭滑线的原理、结构入手,对封闭滑线在国电石嘴山发电厂装卸桥的实际应用中,有关温度变化、运行速度以及支架的稳定性所出现的弊端进行了分析;并从大量的实践经验出发,提出了一些独特的观点和分析方法。
Starting with the princip les and structure of closed side-line, analyzes the abuses in temperature change, running speed and stability of bracket for closed slide-line applied in loading and unloading bridge of Shizuishan Electric Power Plant, based on plentiful field experience, puts forward some unique idea and analysis methods.
出处
《宁夏电力》
2006年第4期65-67,72,共4页
Ningxia Electric Power
关键词
封闭滑线
装卸桥
受电器
移动取电
closed slide-line
loading and unloading bridge
device of receiving electricity
moving getting electricity