摘要
某工程在施工过程中需设置转换,使楼板由200mm经过转换变为800mm,由于楼板超厚,给模板支顶和混凝土浇筑带来许多困难,在施工中通过采用转换板、模板支护体系的设计及各分项工程施工时,相互配合以及一些特殊做法和节点处理等相应措施,保质保量地完成了任务。
In the construction of a project, transferring floor is arranged to change the floor thickness from 200mm to 800mm. Supper slab thickness brought difficulties to the formwork erection and concrete placement. By adopting transferring slab, co-ordination in the formwork design and works construction and node treatment as well as some special methods, the work was completed in good quality.
出处
《建筑技术》
北大核心
2006年第9期695-697,共3页
Architecture Technology
关键词
转换板
混凝土
支撑
problemboard
concrete
crutch