无碴轨道钢筋混凝土桩网地基加固施工技术

Foundation-reinforcing Engineering Techniques for Ballastless Track Reinforcing Concrete Pile Mesh
下载PDF
导出
摘要 介绍了钢筋混凝土桩网复合地基加固技术的机理、工艺以及在我国第一条无碴轨道试验段上的应用情况。结合工程实例,阐述了采用长螺旋钻机在岩层中成孔,用电流法控制钻头的入岩深度以及利用钻机进行先灌混凝土后插钢筋笼等关键施工技术,为我国的客运专线建设提供借鉴。 This article introduces the theory and technology of the concrete pile mesh compound foundation-reinforcing technique of and its practical application in the first ballastless track test section in our country. In the light of engineering examples, this article describes such key construction techniques as hole forming in rock stratum with long spiral auger, rock-entering depth of drilling head controlled with method of electric current, and concrete casting carried out before reinforcing cage inserted with the tool of driller, which provides meaningful experiences for the construction of passenger transport line.
作者 赵天启
出处 《铁道建筑技术》 2006年第4期60-62,共3页 Railway Construction Technology
关键词 无碴轨道 地基加固 电流法 反插钢筋笼 ballastless track foundation reinforce method of electric current counter-insert reinforcing cage
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部