摘要
索风营水电站坝址区岩溶发育,防渗帷幕工程施工难度大,为节省工程投资,采用水泥粉煤灰混合浆液进行防渗灌浆施工,监理工程师如何控制防渗帷幕工程的质量,本文进行了较为系统的论证。
Karst has very developed in the dam area of Suofengying Hydropower Station, therefore, there are a lot of difficulties in construction of anti-seepage curtain project. In order to cut down the engineering cost, a kind of cement grout mixing with ash fly was adopted in construction of the anti-seepage curtain. The article systematically introduces how the supervision engineer controlled the quality of anti-seepage curtain engineering.
出处
《贵州水力发电》
2006年第4期66-70,共5页
Guizhou Water Power
关键词
水利工程施工
防渗帷幕
质量控制
索风营水电站
conservancy engineering construction
anti-seepage curtain
quality control
Suofengying Hydropow- er Station