通过采用钢框模板结合水下不离析混凝土以及对玻璃钢夹砂排水管采用抱箍的施工方案,成功解决了在较短工期内完成抛石棱体中出水口施工难度大的问题。
Adopting the construction scheme which combines iron-frame moulded board with unsegragating concrete underwater and encircling steel hoop on glass fiber reinforced plastic mortar pipes, the difficulty in construction of outfall in riprap mound within a short period period is overcome.
出处
《水运工程》
北大核心
2006年第9期81-84,共4页
Port & Waterway Engineering
关键词
抛石棱体
出水口
施工技术
riprap mound
outfall
construction technique