摘要
根据圆形挖孔桩护壁厚度计算公式,介绍了应用vb编程语言编制的电算程序,根据算例,分析比较了程序计算与手工计算的效果,得出电算具有的优越性,根据电算结果,得出了不同桩基深度可采用不同厚度的护壁这一结论。
According to well-coat thickness calculation formula of circular dug out pile the calculation program prepared by VB language is introduced. Combined with example calculation results of program and artificial handling are comparatively analyzed, which show former method is good. Program calculation results show the thickness of well-coat can vary with the depth of pile foundation.
出处
《山西建筑》
2006年第19期356-357,共2页
Shanxi Architecture
关键词
圆形挖孔桩
护壁厚度
输入参数
手工计算
circular dug out pile, thickness of well-coat, input parameter, artificial handling