钢管砼顶升法冬期负温施工

Steel tube concrete column lift-up method construction at negative temperature in winter
下载PDF
导出
摘要 针对钢管与砼膨胀系数的差异(分别为1.2×10-5/℃和0.7×10-5/℃),阐述低负温(-5℃至-17℃)下钢管砼柱砼顶升法施工原理、热工计算、外加剂选择以及开孔排气、压力灌浆等关键工艺方法步骤。最后,作出砼强度数理统计分析和技术经济效果评述。可供同类结构施工参考。 Aimed at difference of expansion coefficient between steel tube and concrete (1.2×10^-5/℃ and 0.7×10^-5/℃ respectively), some key process method and step under low temperature ( -5 ℃ to - 17 ℃ ),scuh as state construction principle of steel tube concrete column lift up, heat count, selection additive agent and cut exhaust opening and draining air, pressure grouting etc were elaborated. Finally, mathematical statistics analysis was made and effect of technology economy was estimated, which can be taken as reference of the same kind construction.
出处 《鞍山科技大学学报》 2006年第3期287-289,共3页 Journal of Anshan University of Science and Technology
关键词 复合外加剂 顶升压力 排气孔 效果评述 composite additive agent lift-up pressure air exhaust hole effect estimation
  • 相关文献

参考文献4

二级参考文献5

共引文献80

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部