摘要
污水处理厂的处理规模是影响工艺选择、基建费用和运行管理费用的决定性因素,而地下水的渗入量又是影响处理规模的重要因素。以南太子湖污水处理厂为例,在实时监测的基础上,以节点流量衡算法预测了污水处理厂近、远期的地下水渗入量。
Treatment scale is a decisive factor determining the technical process, construction cost and operation expenses of a wastewater treatment plant. The quantity of groundwater infiltration is an important factor affecting the treatment scale. Taking the Nantaizihu Wastewater Treatment Plant as an example and on the basis of the real-time monitoring, the quantity of groundwater infiltration in recent years and for a long period is predicted using node flow algorithm.
出处
《中国给水排水》
CAS
CSCD
北大核心
2006年第18期45-47,共3页
China Water & Wastewater
关键词
污水处理厂
处理规模
地下水渗入量
预测
wastewater treatment plant
treatment scale
groundwater infiltration quantity
prediction