摘要 惠蓄电站压力钢筋混凝土岔管,结构体形复杂,承受内水压力约7.5 MPa,PD值高达6 000 m2,是本工程关键部位。在广蓄电站压力岔管的基础上,通过分析研究国内外岔管形式,提出6种体形方案,通过水头损失、投资、电能效益、有限元计算等进行分析比较,寻求满足结构安全要求、经济和体形尽量简单的岔管体形。 To Huizhou pumped storage power plant, bifurcated penstock with reinforced concrete fork pipe is the key of this program, ifs pattern and structure are very complex, its ability of endure internal water pressure is about 7.5MPa, and PD value is up to 6000. On the basis of Guangzhou pumped storage power plant, by analyzing the form of the bifurcated pipe in both domestic and overseas, present six pattern schemes. By analyzing the water head loss, investment, electric benefits, finite element analysis etc. , safe, economy and simple bifurcated penstocks pattern of the structure is sought.
作者 黄立财
出处 《中国农村水利水电》 北大核心 2006年第9期121-124,127,共5页 China Rural Water and Hydropower
关键词 抽水蓄能电站 压力岔管 有限元计算 pumped storage power plant, bifurcated penstock, optimization, and finite element analysis
  • 相关文献

参考文献2

  • 1水利电力部.SDJ114-85,水电站压力钢管设计规范[S].北京:水利电力出版社,1985.
  • 2马善定 周润坚 等.混凝土坝下游面钢衬钢筋混凝土压力管道的强度和变形[J].水力发电学报,1988,(4):18-23.

共引文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部