摘要
文中针对武钢热轧厂硅钢步进梁式加热炉液压系统存在的问题提出了几种改造方案,并根据工厂提出的改造原则确定了最佳改造方案。
Several projects were proposed in allusion to the problems which were reflected in the old walking beam heating-furnace hydraulic system in Si-steel mill, and the best of which were confirmed according to the principles proposed by workers in the mill.
出处
《机械工程师》
2006年第10期38-40,共3页
Mechanical Engineer
关键词
步进梁
电液比例控制
液压系统
walking beam
electro-hydraulic proportional control
hydraulic system