摘要
采用爆破挤淤法进行基础处理时,合龙口一直是质量控制的重点和难点。本文介绍了某工程南堤合龙口处理中出现的问题、原因分析、处理方案及效果,从而丰富了爆破挤淤施工的理论和经验。
When the method of mud displacement by blasting is used to improve a foundation, treatment of the final closure is always the key and difficult point for quality control. The paper deals with the problems developed in the treatment of the final closure for the southern dike for a project, analysis of the causes of the problems, plans for solving the problems and results of the treatment, thus enriching the theory and experience of mud displacement by blasting.
出处
《中国港湾建设》
北大核心
2006年第5期59-60,共2页
China Harbour Engineering
关键词
爆破挤淤
合龙口
落底
处理
效果
mud displacement by blasting
final closure
bottom
treatment
result