分析了湖北汉川电厂1号机组主蒸汽管道、再热蒸汽管道、主给水管道及炉顶支吊架的运行现状和存在的问题,并对管道运行安全性的影响进行了评估。提出了支吊架调整方案。
The operating status and the existing problems of main steam pipe,reheat steam pipe,main feed water pipe and the support and hanger of boiler top are analyzed. The impact on the safety of the pipe operation is also estimated. The adjustment scheme of the support and hanger is put forward.
出处
《湖北电力》
2006年第5期27-28,共2页
Hubei Electric Power
关键词
管道
支吊架
应力
调整
pipe
support and hanger
stress
adjustment