用实际操作参数对脱硫装置吸收塔进行的工艺核算,可验证塔板的工艺尺寸是否在适宜的范围,及在规定的负荷范围内能否正常操作并进行技术分析;对实际操作和今后的技术改造具有指导意义。
By checking the process of desulfurization absorption tower with the actual operation parameters, we can validate whether the size of absorption tower is within the appropriate range and the unit normally run within the range of stated load. The conclusion has the guiding meaning to the actual operation and the technique reformation of the future.