摘要
介绍了两种平整场地大型土石方工程中关于三点挖(填)一点填(挖)的工程量计算方法,并根据实例说明了其具体应用,提出了第三种计算方案,经过比较,证明了新方案的简捷与合理性。
Two engineering quantity calculation method of three-point excavation and one-point filling in earthwork project are introduced. According to practical work and application the third calculation scheme is presented. Comparing with two others the third is simple and reasonable.
出处
《山西建筑》
2006年第21期95-96,共2页
Shanxi Architecture
关键词
工程量
挖方量
棱柱体
土方量
engineering quantity, amount of excavation, prism, earth volume