结合锦屏二级水电站的工程概况,从设计前的探洞试验、施工地质超前预报、施工过程的监控量测、信息处理四方面介绍了锦屏辅助洞信恩化的施工技术,为类似大型地下工程提供了经验。
Combined with second-level water power station construction survey in Jinping, in introduces the subsidiary tunnel information construction technique from four aspects of exploratory heading before design, geology leading prediction in construction, monitoring measuration in construction process, data treatment, which will provide experience to the similar large-scale substructure work.
出处
《山西建筑》
2006年第21期287-288,共2页
Shanxi Architecture
关键词
监控量测
初期支护
位移观测数据