项目活动时间估算的适用性研究 被引量:7

The Applicability Analysis of Estimating Project Activity Duration
原文传递
导出
摘要 在项目活动时间三次估算公式的基础上,根据活动时间分布,试图减少一个极端值的估算,得出两次估算方法,以此降低时间估算中的主观性和时间估算的次数,并对两种方法推导出项目活动时间均值和方差的计算路径,同时构造了样本假设检验的方法,在试验的基础上对两种估算进行比较,从而判断和改善项目活动时间估算的适用性。最后通过实证得出当偏差系数小于-0.4或大于0.2时,活动时间估算采用三次比较适宜;当偏差系数位于二者之间时,采用二次估算比较适宜。 In order to reduce one time of estimating extremum and debase subjectivity of estimating activity duration according to activity time distribution, this paper educes the method of two times estimating activity duration on the base of three times estimating formula. Calculating route of project activity time mean and variance is deduced for two kinds of method, and sample hypothesis test method is constructed. It is used to judge and improve the applicability of estimating project activity duration. Finally, based on the experimentation, the paper elicits, it is fitting to use three times of estimating activity duration while the skewness is less than --0. 4 or greater than 0. 2; it is feasible to reduce one time of estimating extremum.
出处 《工业工程与管理》 2006年第5期95-98,共4页 Industrial Engineering and Management
基金 国家自然科学基金资助项目(70272031)
关键词 活动时间 适用性 偏差系数 关键链 Activity Duration Applicability Skewness Critical Chain
  • 相关文献

参考文献10

  • 1马国丰,王爱民,屠梅曾.CCM:一种基于TOC的项目管理技术[J].系统工程理论方法应用,2004,13(2):167-171. 被引量:14
  • 2杰克 吉多.成功的项目管理[M].北京:机械工业出版社,1999..
  • 3AbouRizk S M, Halpin D W. Fitting beta distributions based on sample data[J]. Construction Engineering and Management, 1994, 120(2),288-305.
  • 4Swanson L A, Pazer H L. Implications of the underlying assumptions of PERT[J]. Decision Science, 1971, 2 (10):461-480.
  • 5Littlefield T K, Randolph P H. An answer to Sasieni's question on PERT times[J]. Management Science, 1987, 33(10): 1357-1359.
  • 6Lau A H L, Lau H S, Zhang Y A simple and logical alternative for making PERT time estimates[J], IIE Transactions, 1996, 28: 183-192.
  • 7Callahan M T, Quackenbush D G, Rowings J E. Construction Project Scheduling[M]. New York: McGraw-Hill, 1992.
  • 8Demenais F, Lathrop M, Lalouel J M. Robustness and power of the unified model in the analysis of quantitative measurements[J]. American Journal of Human Genetics, 1986, 38 (2):228-234.
  • 9Moder J J, Phillips C R, Davis E W. Project Management with CPM, PERT and Precedence Diagramming[M]. New York: Van Nostrand Reinhold. 1989.
  • 10Benjamin J R, Cornell C A. Probability, Statistics, and Decision for Civil Engineers[M]. New York: McGraw-Hill, 1970.

二级参考文献8

  • 1潘开灵 尹柳营.用制约因素理论指导企业技术进步[J].中国学术期刊文摘,1997,3(4).
  • 2Goldratt E M. What is this thing called the theory of constraints? [M]. NY: North River Press, 1990.
  • 3Goldratt E M, Cox J. The Goal [M]. Aldershot England: Gower, 1993.
  • 4Goldratt E M. It's Not Luck [M]. Aldershot England: Gower, 1994.
  • 5Goldratt E M. Critical Chain [M]. NY: North River Press Inc, 1997.
  • 6Cotterell S. ProChain project scheduling [J]. Version 1.0. Project Management Today, 1998, June: 31-35.
  • 7Newbold R C. Project management in the fast lane:Applying the Theory of Constraints [M]. Boca Rattm Florida: St, Lucie Press, 1998.
  • 8马国丰,屠梅曾,史占中,吴伟.基于关键链技术的项目进度管理系统设计与实现[J].上海交通大学学报,2004,38(3):377-381. 被引量:35

共引文献18

同被引文献93

引证文献7

二级引证文献53

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部