设备工程监理中进度控制的偏差分析法研究 被引量:1

Time Control Warp Analysis Method in Equipment Engineering Supervision
下载PDF
导出
摘要 为了使设备工程监理中的进度控制方法更加完全,提出了偏差分析法。它包括曲线比较法与投资偏差分析法两种进度控制方法,其中曲线比较法分为S形曲线比较法、香蕉曲线比较法和前锋线比较法。利用这两种进度控制方法,均能直接判断进度状况,并计算出相应的进度偏差值。在某污水处理站的实际应用表明,该方法在进度控制方面取得了很好的效果,完善了设备工程监理的进度控制方法体系。 The time control problem in equipment engineering supervision is discussed. Based on warp analysis, two methods of time control in equipment engineering supervision are presented, one is the curve comparison and the other is cost warp analysis. The curve comparison method includes “S”, “Banana” and vanguard curve. These two methods are used to evaluate the time status and calculate the corresponding time difference. The practical application shows that the proposed methods possess the good properties in equipment engineering supervision.
出处 《控制工程》 CSCD 2006年第6期594-595,共2页 Control Engineering of China
关键词 设备工程监理 进度控制 偏差 equipment engineering supervision time control warp
  • 相关文献

参考文献2

  • 1Viktorsson A Z,Hovmark S,Nordqvist S.Psychosocial aspects of project work:a comparison between product development and construction projects[J].Journal of Project Management,2003,21(8):563-569.
  • 2Merwe V D.Project management and business development:intergrating strategy,structure,processes and projects[J].International Journal of Project Management,2002,20(2):401-411.

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部