摘要
阳江核电站位于广东阳江市东南35km,5条排水隧洞为核电站的冷却水排水通道,是核电站的关键项目,其能否如期完工,关系到核电站能否按期发电,搞好施工组织设计工作尤为重要。阳江核电站排水隧洞工程的设计,也是我国水电设计行业在核电站设计领域进行的一次有效的尝试,成功的设计工作势必为推动我国核电事业的发展做出积极的贡献。
Yangjiang nuclear power station is located at southeast part of Yangjiang city and it is 35km from Yangjiang City of Guangzhou. 5 drainage tunnels are the cooling water drainage channels of the nuclear power station and they are the key projects of the nuclear power station.Whether the project can be completed on time is related to the generation of power on time, therefore, it is very important to do the construction mobilization and the design work well. The design of drainage tunnel project for Yangjiang nuclear power station is the first effect trial in nuclear power station design field by the designers from hydropower design field, so the successful design work will promote us to do active contribution to the development of the nuclear power cause of our country.
出处
《水利水电工程设计》
2006年第4期7-9,55,共3页
Design of Water Resources & Hydroelectric Engineering
关键词
排水隧洞
施工组织设计
阳江核电站
Drainage tunnel, construction mobilization and design, Yangjiang nuclear power station.