武广客运专线140 m下承式钢箱系杆拱桥拖拉施工方案探讨 被引量:4

Study of Construction Schemes for Hauling Erection of 140-m Span Through Steel Box Tied Arch Bridge on Wuhan-Guangzhou Passenger Dedicated Railway
下载PDF
导出
摘要 武广客运专线140 m下承式钢箱系杆拱桥上跨双向4车道京珠高速公路,桥轴线与京珠高速公路斜交,要求在全桥钢箱系梁、纵横梁、钢箱拱和吊杆安装完后再进行拖拉就位。采用ANSYS程序对2种拖拉施工方案施工全过程进行模拟计算,从临时墩设置、临时墩支座反力、导梁、纵横梁以及吊杆受力特点等方面进行分析研究。 The 140 m span through steel box tied arch bridge on Wuhan-Guangzhou Passenger Dedicated Rail spans the dual two lane Beijing-Zhuhai Expressway and the axis of the bridge is skew to that of the Expressway. In the construction, the bridge is required to be erected by hauling construction method after the installation of the steel box tied beams, longitudinal and transverse beams, steel box arches and hangers of the whole bridge has been completed. In this paper, the ANSYS program is used to conduct simulation calculation of the whole construction process of the proposed two kinds of the hauling construction schemes and the analytic study is made as well from aspect of setting of the temporary piers, reaction forces of the bearings on the temporary piers, and structural behavior of the launching noses, longitudinal and transverse beams and hangers.
作者 黎顺生
出处 《桥梁建设》 EI CSCD 北大核心 2006年第A02期124-127,共4页 Bridge Construction
关键词 系杆拱桥 拖拉施工 施工方案 tied arch bridge hauling construction construction scheme
  • 相关文献

参考文献2

二级参考文献3

共引文献10

同被引文献30

引证文献4

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部