摘要
分析大秦线2万t重载组合列车采用LOCOTROL技术的运用情况。介绍了LOCOTROL装备的工作原理,结合大秦线有关试验、计算和运行情况,分析不同编组的2万t重载组合列车动力学性能。讨论LOCOTROL装备的延迟时间对重载组合列车性能的影响,针对大秦线开行2万t重载列车的安全问题提出建议和对策。
The application of LOCOTROL technology for 20 000 t heavy haul trains on Datong-Qinhuangdao railway line is analyzed in this paper. The working principle of LOCOTROL equipment is explained. According to line tests, simulation and real train running on Datong-Qinhuangdao railway line, the dynamic performance of different train deformations for 20 000 t heavy haul trains is studied. The influence of delay time of LOCOTROL equipment on the performance of heavy haul trains is discussed. Some suggestions and solutions are presented, which are useful to the safety of 20 000 t heavy haul train.
出处
《电力机车与城轨车辆》
2006年第6期5-7,41,共4页
Electric Locomotives & Mass Transit Vehicles
关键词
大秦线
重载列车
组合列车
LOCOTROL
Datong-Qinhuangdao railway line
heavy haul train
combin
train
LOCOTROL