摘要
介绍了鞍钢新2号、新3号高炉运上料皮带机安装与调试的程序和方法,总结了科学、高效安装皮带机的经验,并对皮带机调试运行过程中的跑偏现象进行了研究,提出了快速诊断、调整的方法。
This paper describes the course and methods to install and adjust charging belt conveyors of Angang New No. 2 and No. 3 BFs, summarizes scientific and efficiency experiences to install belt conveyor, studies the snaking phenomenon on belt conveyor during adjustment and operation and represents quick diagnosis and regulation methods.
出处
《鞍钢技术》
CAS
2006年第6期37-41,共5页
Angang Technology
关键词
高炉
皮带机
安装
空载试车
BF belt conveyor installation no-load commissioning