重庆石板坡长江大桥复线桥主跨(330 m)的103 m钢箱梁段为整体吊装合龙,在温度变化下的大尺寸合龙是技术难度较高的工作。介绍在桥梁设计中对合龙的考虑和实施结果。
The 103 m long portion steel box girder structure for the main span (330 m in length) of the double-line bridge of Shibanpo Changjiang River Bridge in Chongqing is erected and closed by heavy lifting method. The closing of such huge size structure under condition of varying temperatures is indeed a technical challenge. In this paper, the considerations for the closing con struetion in the design of the bridge and results of the implementation of the closing are dealt with.
出处
《桥梁建设》
EI
CSCD
北大核心
2006年第6期33-36,共4页
Bridge Construction
关键词
刚构-连续梁桥
箱形梁
混合梁
钢梁
合龙
设计
rigid-frame structure and continuous girder bridge
box girder
hybrid girder
steel girder
closing
design