上海廖创兴金融中心大厦深基坑工程逆作法的实测与研究 被引量:10

A MONITORING AND STUDY ON UP AND DOWN CONSTRUCTION METHOD FOR THE DEEP EXCAVATION OF BUILDING IN SHANGHAI LIAOCHUANGXING FINANCIAL CENTER
下载PDF
导出
摘要 通过对上海廖创兴金融中心大厦面积为5 151m2的深基坑工程逆作法施工的墙体水平位移、基坑底隆起、墙顶和邻近立柱桩以及立柱间的差异位移、水平支撑轴力和楼板应力的大量实测数据,以理性和经验进行分析研究,得出深基坑工程逆作法施工有别于顺作法施工的应力和变形的明显特点,提出改进逆作法施工的基坑设计的建议,供类似工程参考。 In a 170.10m high and 37-storey super-tall building with 3-storey podium, excavation depth of 22.4 - 28.4m and an area of 5 151m^2 in Shanghai, based on the theoretical concept and experience, it is analyzed that a great deal of monitoring results for horizontal displacements, bottom heave, differential displacements between diaphrgam wall and adjacent mid-post pile and between mid-post piles, bracing axial force and stresses in slab of floor for special deep excavation, and significant characteristics of stress and displacement for up-down construction method differing with normal construction method are also been obtained. ,Some suggestions on improving the design of up-down construction method for deep excavation engineering are presented,which may be an impartant reference for other similar projects.
出处 《工业建筑》 CSCD 北大核心 2006年第12期44-49,共6页 Industrial Construction
关键词 逆作法 深基坑工程 水平位移 坑底隆起 差异变形 支撑轴力 楼板应力 up-down construction deep excavation engineering horizontal displacement bottom heave differential displacement bracing axial force stress in floor slab
  • 相关文献

参考文献2

  • 1上海市人大常委会.上海市轨道交通管理条件[OL].(2004-04-08)[2005-01-08].http://www.shjsgh.gov.cn/regulation/detail.asp?NewsId=82
  • 2赵锡宏.现代深大基坑设计理论、实践与案例分析//深基坑支护技术专题研讨会论文集.北京:2006:1-65

同被引文献74

引证文献10

二级引证文献43

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部