摘要
通过对近年来,特别是2004年500 kV电网风偏事故的分析研究,针对我国500 kV输电线路龙政直流线路故障,结合国外风偏的计算方法,分别进行了计算分析,提出了一些看法和建议。
Through the analysis and study of the windage yaw fault of 500 kV transmission line in recent years particularly in 2004,in view of the 500 kV HVDC Long-zheng transmission lines fault in our country,in connection with the calculation method from abroad, each windage yaw fault was calculated and analyzed. Views and suggestions were presented as well.
出处
《湖北电力》
2006年第6期46-48,共3页
Hubei Electric Power
关键词
500
KV电网
风偏闪络
风偏计算
500 kV power system
flashover due to windage yaw
calculation of windage yaw