根据电站的实际生产要求,研究了公伯峡水电站节水增发的考核指标及关键考核参数的推求方法,并针对当前根据设计值进行估算的办法,提出了采用典型时段发电过程模拟计算确定考核参数的新方法。在此基础上,采用VB软件开发出了公伯峡水电站节水增发考核系统,用户可任意指定考核起止时段。算例结果表明,本考核系统结果合理,运行稳定。
The assessment target, assessment model and computing method for water economization and improving power generating on Gongboxia power station are investigated in this paper respectively on the basis of practical production conditions. Also, aiming at the estimation method based on the current designed values, a new method for determing the assessment parameters is suggested using the simulation calculation in typical time-section power generating process. On the basis of which, VB software is used to develop the assessment system of water economization and power generating improvement of Gongboxia power station so that the users can specify the time section of assessment starting and stopping at random. The results from the calculated examples indicate that the results of assessment system are rational and its operation is stable.
出处
《西安理工大学学报》
CAS
2006年第4期399-402,共4页
Journal of Xi'an University of Technology
基金
国家自然科学基金资助项目(50679070)
关键词
节水增发
发电负荷率
考核水位
相对水能利用率
水能利用提高率
water economization and power generating increase
generating charge rate
assessment water level
relative energy use efficiency
energy utilization improvement rate