摘要
对安钢动力厂6000kW汽轮发电机组运行中凝结器水位(即热井水位)监测和控制中存在的问题进行了分析,提出并阐述了相应的改进措施,实践表明,改进后控制结构合理、系统稳定、效果良好。
This article analyzed the existing problem in water level monitoring and continlling during the turbine running of AnGang Motive Power factory 6000kW turbine generator set ,Improving method are proposed and pointed out accordingly. It is proved by practice that the improving method is reasonable and the system works stably ,perfect effect are achieved.
出处
《河南冶金》
2006年第6期52-53,共2页
Henan Metallurgy