摘要 周宁水电站具有长隧洞、高竖井、高水头等工程特点,设计采用了超高压竖井,压力管道取消钢衬,采用钢筋混凝土岔管,透水衬砌设计,高压固结灌浆,直螺纹钢筋连接,地下厂房岩壁梁等技术,实践表明,这些技术措施经济可行,许多方面处于国内领先水平。 Zhouning Hydropower Station is charactized with long tunnels, high shaft, and high water head. Key technologies have been adopted in its design, such as super high pressure shaft, canceling steel lining in pressure tunnel, using of concrete Y-type pipe, designing of permeable lining, high pressure consolidating grouting, indented steel bar butting, beam on rock wall in underground power house. It has been proved in practice that these technological measures are economical and feasible,some of which are in leading position is China.
出处 《水力发电》 北大核心 2006年第12期64-66,共3页 Water Power
关键词 高水头 超高压竖井 高压管道衬彻 地下洞群 关键技术 周宁水电站 high water head super high pressure shaft high pressure tunnels underground caverns key technologies Zhouning Hydropower Station
  • 相关文献

参考文献1

  • 1肖明,俞裕泰.地下钢筋混凝土岔管和高压管道衬砌结构研究[R].武汉:武汉大学.2001.

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部