摘要
根据青岛国际帆船中心陆域建筑—奥运村地下室工程的工期要求,结合青岛地区夏季多雨水的实际特点,采用堵截雨水进入地下室以确保施工正常进行,并通过对土建、安装、装修各工序的合理组织穿插施工,绘制网络图并随工程实际进展不断进行网络优化,最大限度地节约了资源,缩短了工期,确保了奥运村超大型地下室的按时完成.
According to the 29th session of Olympic Games Qingdao International Sailing Ship Center Lu Yu, and the summer multi-rains water actual characteristics in Qingdao area, the Olympic Village basement project time limit for project requirement, the construction goes by blocking off the rain water from flowing into the basement to guarantee a normal construction. And through the construction, the installment, various working procedures, the reasonable organization, the network chart and the network optimization, maximum resources saving, the reduction of time limit for project, the Olympic Village ultra large-scale basement will be guaranteed in accordance with the contract requirement.
出处
《青岛理工大学学报》
CAS
2006年第6期49-53,共5页
Journal of Qingdao University of Technology
关键词
奥运村
超大型地下室
堵截雨水
穿插施工
高压缩工期
施工环境条件
施工控制点
Olympic Village, ultra large basement, blocks off the rain water, alternation construction, high compression time limit for a project, construction environmental condition