摘要 沉井是软土地基中深基础施工方法之一,在工程用地与环境条件受到限制或埋深较大的地下构筑物工程中被广泛应用。为满足布置要求,沉井时常常碰到超越规范要求或者碰到施工工期不合理、施工场地有限的时候。本文通过规程规范及专业手册,结合多年来的工程实践,简述沉井工程在施工中的一些体会、心得及工程经验的积累,并介绍一个沉井结构成功的实例,供大家探讨并作为今后类似工程参考和借鉴。 Sink well is one of built method in deep foundation of soft groundwork, It is used widely in limited ground and limited environment or in deep burying construction. It is contacted with the things exceed criterions or some unspecific items in criterions or inconsequence construction time limit for a project or limited construction field in order to satisfied arrangement. Some experiences in construction of sink well states simply through rules and criterions and speciality handbooks combined with practices in many years. A successful example is provided for discussed and used for reference.
作者 高玲
机构地区 华东电力设计院
出处 《电力勘测设计》 2006年第6期21-24,共4页 Electric Power Survey & Design
关键词 沉井 保护措施 裂缝 sink well protection measure crack.
  • 相关文献

参考文献4

  • 1CECS137:2002给水排水工程钢筋混凝土沉井结构设计规程.
  • 2DGJ08-11-1999.地基基础设计规范.[S].,..
  • 3NDGJ5-88.火力发电厂水工设计技术规定.
  • 4[4]SDJ280-90,电力建设施工及验收规范(水工结构篇)[S].

共引文献23

同被引文献6

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部