影响巷道施工方案选择的因素多而复杂,施工方案决定了巷道的安全质量、建设成本和施工进度。通过建立多层次的模糊综合评判模型,用模糊分布法、最大隶属度原则对非数字化的各因素,客观、准确地加以定量和评判,实现事先控制,为工程实践建立理论依据以指导巷道施工建设。通过实例验证了模型所得结论的正确性。
The factors influencing the choice of laneway construction projects are excessive and complex since the project decides the safety, the costs and the execution progress. The article, based on the multilayer fuzzy synthetic model of judgment, uses fuzzy distribution and the biggest subjection to quantify and judge the non-figure factors objectively and exactly. The beforehand control is realized. It is proved with actual examples that the conclusion based on the model consists with the result of the actual construction, and the correctness of the model is validated.