结合贵广Ⅱ回直流工程白花洞换流站地基处理工程设计实际,通过对在地形、地质复杂条件下的换流站的建(构)筑物地基处理设计情况介绍,提出了换流站地基处理设计中的一些控制要点和需要注意的事项。
Based on the actual case of the foundation treatment engineering design of Baihuadong Converter Station in Gui- Guang Ⅱ line HVDC power transmission project, and according to the introduction about how to do foundation treatment design of the buildings when the converter station would be in the area with complex geological condition and undulate landform, some control key points and some things should be considered in the foundation treatment design of the converter station are presented, besides, several modification process and result in design, and some modification explanation are discussed.