张双楼副井冻结法穿过膨胀性厚黏土层施工技术

Construction technology of freezing method for mine auxiliary shaft in Zhangshuanglou Mine passing through swelling thick clay layer
下载PDF
导出
摘要 介绍了张双楼矿副井冻结和施工穿过膨胀性厚黏土层所采取的安全技术措施、施工方法、厚黏土层掘砌问题及处理措施。提出了冻结法穿过膨胀性厚黏土层应注意的问题是:提高制冷能力、加速井中冻实;缩短井壁段高,减小暴露时间;检测盐水温度,确保冻结正常;提高外壁强度,增强抵抗能力;综合分析资料,合理确定方案。 The paper introduced the safety technology measures, construction methods, thick clay excavation issues and treatment for the mine auxiliary shaft freezing and sinking through swelling thick clay layer in Zhangshuanglou Mine. The paper provided the issues for freezing method passed through swelling thick clay layer: to improve the refrigeration capacity, to firmly freeze the ground in the shaft, to reduce the section height of operation, to reduce the exposed time, to check the salt water temperature, to keep a normal freezing, to improve the strength of the outer wall, to improve anti capacity, to analyze the information and rationally set the alternative.
作者 万援朝
出处 《煤炭科学技术》 CAS 北大核心 2007年第1期38-41,共4页 Coal Science and Technology
关键词 副井 冻结 膨胀性 黏土层 mine auxiliary shaft freezing swelling clay layer
  • 相关文献

参考文献3

  • 1王长生,苏立凡,张文.地层冻结工程技术和应用[M].北京:煤炭工业出版社,1995.
  • 2张世芬,李功洲,陈文豹.宁夏矿区深厚冲积层特殊凿井技术[M].北京:煤炭工业出版社,2003.
  • 3岳孝方,陈汝东.制冷技术与应用[M].上海:同济大学出版社,1996.

共引文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部