祁东煤矿东风井基岩段注浆防治水技术 被引量:5

Water prevention and control technology with grouting for base rock section of East ventilation shaft in Qidong Mine
下载PDF
导出
摘要 祁东煤矿东风井井筒基岩段穿过2层中粒砂岩含水层,其中第一含水层处于有效冻结范围内,对第二含水层采用工作面预注浆法进行施工,通过提高止浆垫混凝土标号、合理选择钻注顺序和浆液浓度、提高注浆压力、调整注浆段高划分等措施,缩短了注浆工期,确保了注浆效果。 The base rock section of East Ventilation Shaft in Qidong Mine passed through 2 medium particle sandstone aquifers. The first aquifer was in the section of the ground freezing area and the second aquifer would be sunk through with the pregrounting at the face. With the higher quality concrete for the grouting cover, the rational drilling program and the grouting density, the higher grouting pressure, the adjustment of grouting section height and other measures, the grouting operation period was reduced and the grouting results was ensured.
出处 《煤炭科学技术》 CAS 北大核心 2007年第1期68-70,共3页 Coal Science and Technology
关键词 工作面预注浆 砂岩 含水层 pregrouting at face sandstone aquifer
  • 相关文献

同被引文献19

引证文献5

二级引证文献62

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部